Columbia Gas is upgrading more than 5,000 feet of old steel pipe in the Hilltop communities in the coming months.

Work began last week and will continue until late December on Freeland Street, Loyal Way, Knox Avenue, Arlington Avenue, Amanda Avenue and Mount Oliver Street. Work will be underway Monday – Friday from 8 a.m. to 5 p.m. Traffic will be affected with single lane restrictions during working hours only.

A minimum of 72-hour notification will be given before customers’ gas service will be turned off one at a time for several hours. Columbia Gas will perform re-light work on appliances.

The project will impact approximately 129 residential and commercial customers.

 